Queen Mary
Posted: Wed Jun 09, 2021 7:08 pm
Urgent Repairs Needed to Queen Mary, Potential Flooding & Capsize Risk
The ex-Cunard luxury liner Queen Mary, which had served as a tourist attraction and hotel in Long Beach, CA since 1972, was shut down by the pandemic. Then in January, the manager of the ship on behalf of the City of Long Beach filed for bankruptcy. Now, the Long Beach Post reports that a recent Queen Mary inspection survey reveals that urgent repairs have been neglected over the last five years, leaving the historic ship vulnerable to flooding or possibly even capsizing if critical work isn’t addressed.
The report from a city-hired naval architecture and marine engineering firm Elliott Bay Design Group, which inspected the ship on April 28, says the city would need an additional $23 million in urgent safety repairs to keep the ship “viable” over the next two years.
That’s on top of the $23 million in bonds and Tidelands funds that the city issued to former operator Urban Commons in 2017 to fix some of the most critical repairs listed in a marine survey. The funds ran out before many of the repairs were completed, and now, the latest report says most of the urgent structural work hasn’t even started as the ship slips into further disrepair.
Continues at:
http://www.oldsaltblog.com/2021/06/urge ... more-57703
The ex-Cunard luxury liner Queen Mary, which had served as a tourist attraction and hotel in Long Beach, CA since 1972, was shut down by the pandemic. Then in January, the manager of the ship on behalf of the City of Long Beach filed for bankruptcy. Now, the Long Beach Post reports that a recent Queen Mary inspection survey reveals that urgent repairs have been neglected over the last five years, leaving the historic ship vulnerable to flooding or possibly even capsizing if critical work isn’t addressed.
The report from a city-hired naval architecture and marine engineering firm Elliott Bay Design Group, which inspected the ship on April 28, says the city would need an additional $23 million in urgent safety repairs to keep the ship “viable” over the next two years.
That’s on top of the $23 million in bonds and Tidelands funds that the city issued to former operator Urban Commons in 2017 to fix some of the most critical repairs listed in a marine survey. The funds ran out before many of the repairs were completed, and now, the latest report says most of the urgent structural work hasn’t even started as the ship slips into further disrepair.
Continues at:
http://www.oldsaltblog.com/2021/06/urge ... more-57703