Development of the Queen Elizabeth class aircraft carrier – a design history
In this article, we review how the design of the Queen Elizabeth Class (QEC) aircraft carriers evolved. This is a broad subject, worthy of several books but this article provides an overview.
Given their size and limitations, the three Invincible class carriers (CVS) had served the nation very well but by the late 1990s consideration of how to replace them was being discussed. In 1997 the MoD began some outline concept studies for potential future carriers. At this stage, it was accepted they would be considerably bigger than the CVS and most likely operate VSTOL aircraft, although a conventional carrier operating Boeing F/A-18E Super Hornet or even a navalised ‘Sea Typhoon’ were briefly considered. Operational analysis suggested that 50 aircraft would be needed to ensure campaign success in medium-intensity scenarios and would probably require a ship displacing at least 38,000 tonnes. Probably for the benefit of the Treasury, the MoD did, however, examine life extension refits and hull-stretching the CVS but unsurprisingly in 1999 concluded that the hulls were too old and lacked the beam to comfortably operate larger future aircraft (the JSF eventually grew to twice the size of the Harrier).
The decisions of the 1998 Defence Review were generally sound and promised the navy would have “two 40,000 ton aircraft carriers, with a complement of up to 50 aircraft and helicopters each. The first will have an in-service date of 2012”. The Future Aircraft Carrier project to build the CVF was formally launched in January 1999. In the light of the capabilities forecast for the QEC by the mid-2020s it is interesting to reflect on how closely they will fulfil the 9 original Key User Requirements (KUR) that were laid down in 1999.
Interoperability – able to contribute to joint and international operations
Integration – able to integrate with the joint battlespace and support air group operations with command, control, communications and intelligence functions
Availability – able to provide one operational ship available at all times
Deployability – able to deploy worldwide
Sustainability – able to mount sustained operations
Aircraft – able to deploy offensive air power without host-nation support
Survivability – have a high probability of surviving damage
Flexibility – able to operate the largest possible range of aircraft
Versatility- able to operate in the widest range of roles.
Design competition
The assessment phase began at the end of 1999 with initial £5.9M Analysis of Options contracts awarded to two consortia lead by British Aerospace (now BAE Systems) and Thomson-CSF (now Thales). This was followed by the award of a second year-long £30M assessment phase contract to both teams in July 2001.
There was considerable scope for creativity and innovation and the only major stipulations beyond the KURs were that the ship must be built in Britain, carry up to 48 aircraft, be single-hulled and not nuclear powered. Affordability was obviously a major consideration and through-life costs were to be given very high priority. Because the crew is such a major factor in the cost of ownership, a target ships company of around 600 was suggested by the MoD. Both consortia gave this considerable attention and the resulting low manpower requirement is a major achievement.