UK carrier strike – full operating capability on final approach
The UK Carrier Strike capability is nearing a critical milestone. Full Operating Capability (FOC) for the F-35B should be achieved during the forthcoming CSG25 deployment. Here we look at latest progress with the jet and the wider carrier strike capability development.
Lightning FOC
According to the annual Government Major Projects Portfolio report published in January 2025, FOC for F-35 was progressing but was rated ‘amber’, indicating risks in meeting the deadline. The specialised nature of the airframe, which combines complex stealth coatings, vertical lift hardware, and high-voltage electronic systems, places exceptional demands on maintainers. Efforts to boost retention and attract qualified personnel have been launched, but results will take time to materialise.
FOC for the F-35B is defined as the ability to deploy two squadrons simultaneously to separate global theatres. The two existing frontline squadrons, RAF-badged 617 and RN-badged 809 Naval Air Squadron must be fully trained, equipped, and certified to operate from either carrier or land base. An RAF statement published this week implies FOC will be achieved: “Operation Highmast is poised to be a landmark event, with plans to declare full operational capability (FOC) for both the jets and the Carrier Strike Group within the year”.
The two front-line units are based at RAF Marham together with 207 Squadron operational conversion unit (OCU), while 17 Squadron conducts test and evaluation work from Edwards AFB in California. Although with many caveats, the Lightning Force is maturing slowly. 617 Squadron is now commanded by a Royal Marine, Lt Col Mike Carty, the first RM to lead a fighter squadron in the UK. 809 Squadron which recommissioned in December 2023 is commanded by Cdr Mick Smith and will deploy, having declared Initial Operating Capability.
The F-35B’s integration with the Meteor beyond-visual-range air-to-air missile will mark a significant leap in the aircraft’s lethality. Flight tests carried out at NAS Pax River during November 2024 have confirmed the successful carriage and release parameters of Meteor from the F-35s internal weapons bay, paving the way for future full integration. Once fielded on F-35, this combination will offer unmatched reach and kill probability in contested airspace.
The Meteor integration process is closely tied to the F-35 Block 4 upgrade, which includes the Technology Refresh 3 (TR-3) hardware suite. This upgrade is necessary to support Meteor and the SPEAR-3 precision stand-off missile, but delays in the software to accompany the TR-3 development have impacted the overall timeline for these integrations. F-35 must fly without Meteor or SPEAR-3, probably until 2030, a scandalous situation impacting the power and reach of the whole carrier programme but the MoD has little power to accelerate progress.
At present, the Lighting force has 35 jets and deliveries of the remaining jets that make up the first tranche of 48 are expected to conclude by the end of this year. In parallel, discussions are underway for a second batch of 27 aircraft, subject to the decisions of the now much-delayed SDR. If secured, this would bring the future fleet to 74 aircraft by the early 2030s. A third operational squadron is also planned, though its identity and formation timeline remain undisclosed.
Crowsnest debacle
https://www.navylookout.com/uk-carrier- ... -approach/