THE TYPE 45 - BEING PATCHED UP BUT STILL TROUBLE PRONE...
The Type 45 (Daring-class) destroyers entered service without a full shore-based test rig for their power generation/propulsion system.
The ships use an innovative Integrated Electric Propulsion (IEP) setup: two Rolls-Royce WR-21 gas turbines (GTs) and two Wärtsilä diesel generators feeding electric motors. To save time and money, the Ministry of Defence and industry skipped building a complete land-based test rig that would have simulated the full integrated system under real-world loads and conditions (relying instead on partial demonstrators and computer modelling). This was explicitly called out as a "disastrous shortcut" in later analyses - it could also be described as a level of incompetence, and shortcuts, almost beyond belief. Problems only fully emerged during sea trials and early operations.
They kept breaking down primarily because of a fundamental design flaw in the WR-21 gas turbines' intercooler-recuperator unit (supplied by Northrop Grumman).
Rear Admiral Chris Parry on Talk News states "These Type 45 are in such a bad state because of political decisions made in the last Labour government. I was there when decisions were made what equipment was put into these ships, the fact that all the money went on the air defence system, and nothing else really was given proper weight and attention, and they were put into service. I should also add that we were originally going to have twelve of them, and it was cut down to six. If we had twelve of them today, I doubt that any of them would be ready for action because of the manifest problems that actually exist on the ships themselves. I mean underwater they are supposed to be quite silent in relation to detection by submarines [when in reality] they sound like a box of spanners because it was neglected in noise hardening as we call it and acoustic hygiene."
https://www.youtube.com/watch?v=y-Ply1kAT24&t=331s
The WR-21s are efficient in cooler waters (they recover exhaust heat to boost performance and reduce the ship's infrared signature). But in warm seawater/air (e.g. Persian Gulf, where ambient temperatures push the system beyond its design limits), the intercooler can't cool the intake air properly. This causes the GTs to overheat, lose power, or shut down. When that happens, the entire electrical load shifts to the two original diesel generators, which weren't sized to handle it alone. They overload and "trip out," resulting in total blackout — no propulsion, no weapons, no sensors. The system was supposed to "gracefully degrade" in heat; instead it failed catastrophically.
This wasn't just "teething trouble." Multiple ships (Daring in 2010/2012, Dauntless in 2014, Duncan in 2016, Diamond in 2016/2024, etc.) suffered repeated power losses, sometimes leaving them dead in the water in high-threat areas and when part of task or strike groups. Early workarounds (Equipment Improvement Plan) helped a bit by restricting operations, but they didn't solve the root cause. The class had notoriously poor availability at times (as low as ~17% in extreme cases).
WORKAROUND:
The refit (Power Improvement Project, or PIP) is a workaround, and the refit process itself has been trouble-prone — but it's now delivering results.
The Power Improvement Project (contracted around 2018–2019, ~£160–189 million) doesn't fix the GT intercoolers themselves, as many state. Instead it:
Replaces the two original diesel generators with more powerful, reliable ones.
Adds a third diesel generator per ship.
Upgrades the high-voltage electrical distribution system.
This gives the ship enough backup generation to keep running (and fight) even if one or both GTs degrade in heat. It's a pragmatic "add more diesels" fix rather than a full engine redesign.
However, because the Type 45s were built as a tightly integrated (non-modular) design, fitting the new generators requires cutting large access holes in the hull, major internal reconfiguration, and complex systems integration. This has made the refits extremely lengthy and expensive in practice:
HMS Daring was unavailable for over 3,000 days (~8+ years) at one point due to compounded issues and being an early PIP guinea pig.
The programme has dragged on, with ships rotated through refit while trying to maintain operational commitments.
As of December 2025, only three ships (Dauntless, Daring, and Dragon) had completed PIP; Defender and Diamond were in refit, and Duncan was still awaiting its turn (scheduled concurrently with its next docking). The target is all six done by 2028.
That said, the upgraded ships are significantly more reliable in hot climates and have restored confidence in the class. The Royal Navy now says the PIP is the "final cure," and availability has improved for the converted hulls. The Type 45s are still planned to serve into the late 2030s.
The lack of proper shore testing let a latent design flaw into service; the breakdowns were predictable once the ships hit warm waters; and PIP is a classic "fix it with more redundancy" engineering workaround that carried its own heavy refit penalties...
The Power Improvement Project (PIP) is explicitly a workaround, not a root-fix for the Type 45 propulsion system.
The core flaw — the WR-21 gas turbines' intercooler/recuperator overheating and failing catastrophically in warm waters — remains untouched. PIP replaces the two undersized original diesel generators with three larger, more capable ones and upgrades the electrical distribution. This ensures that when the GTs degrade or trip (as they still do in hot climates like the Gulf or Red Sea), the diesels can pick up the load without a total blackout. The ship can "gracefully degrade" to diesel-only cruising rather than going dead in the water.
However, the diesels are not a full replacement for the GTs:
They provide less top-end power and sprint speed.
Fuel efficiency and endurance are reduced in diesel-only mode.
The WR-21s are still needed for high-speed operations.
Recent reports (as late as 2026) show upgraded ships like HMS Dragon still suffering "technical issues" that take them offline, and the overall class availability, while improved post-PIP, is not flawless. The refits themselves have been slow and disruptive (Daring alone was out for over 3,000 days).
HMS Dragon suffered from “power cuts and propulsion failures” during her voyage to the eastern Mediterranean. According to The Sun, the 260-strong ship’s company have faced “repeated” faults while battling through gales and 20ft high waves. A source told the national; publication that these were simply “niggles” that were normal whenever a warship sails shortly after a maintenance period.
So yes — the propulsion system retains inherent vulnerabilities; PIP just splits the worst symptom (catastrophic blackouts).
Rear Admiral Chris Parry's comments (from the March 2026 TalkTV interview) are accurate in substance and reflect insider frustration from the procurement era.
Parry was directly involved in the Type 45 decisions as a senior naval officer during the late 1990s/early 2000s.
Here's a breakdown of his points with the documented context:
Political decisions under Labour (1997–2010) and priority on the air-defence system -
This is fair criticism... The Type 45 was conceived post-Cold War as the RN's premier anti-air warfare platform to protect carriers and task groups (hence the world-class SAMPSON radar and PAAMS/Aster missile system). Procurement under the 1998 Strategic Defence Review (and subsequent cuts) deliberately front-loaded the very expensive AAW suite. To stay within tight budgets, other areas — propulsion integration, acoustic quieting, and whole-ship resilience — received less funding and scrutiny.
The risky WR-21 IEP choice and the decision to skip full shore-based system testing were classic examples of this trade-off.
Parry's "I was there" claim holds; these were MoD/Defence Equipment & Support decisions taken under Labour ministers.
Cut from 12 ships to 6.
Completely correct... The original plan (SDR 1998) was for 12 Type 45s to ensure enough hulls for sustained operations (accounting for refits, training, etc.). Cost overruns (each ship ended up ~£1 billion+) and successive budget squeezes saw it slashed first to 8, then to 6 by 2008. This was explicitly a Labour-era decision driven by the 2008 economic crisis and earlier reviews. Multiple admirals and MPs at the time warned it would leave the fleet too thin.
"If we had twelve... I doubt that any of them would be ready for action because of the manifest problems" -
This is Parry's opinion rather than proven fact, but it's a reasonable extrapolation. The design flaws (propulsion, acoustic signature, and the tight integration that made refits painful) were baked into every hull. More ships wouldn't have magically fixed the underlying engineering shortcuts — they'd just have spread the pain wider. The class's early availability was dire (sometimes below 50%, with some ships barely operational for years).
Acoustic hygiene / "box of spanners" underwater -
This is the least publicly documented but widely accepted critique among naval professionals. Type 45s were designed with some stealth features (e.g., rafted machinery, hull shaping) and were meant to be relatively quiet for an AAW destroyer. In practice, the integrated electric propulsion (two large GTs + diesels) and other machinery produce higher radiated noise than ideal for anti-submarine warfare. They are louder than contemporaries like the Type 23 frigates or optimised ASW designs. "Acoustic hygiene" (systematic noise reduction at every stage) was deprioritised to save money and weight while maximising the AAW fit.
The RN does test signatures at acoustic ranges, but the ships have never been the underwater "silent" assets some hoped for. This makes them more detectable by modern submarines (especially in littoral or warm waters where sound propagation changes). It's a real operational limitation when operating in high-threat ASW environments.
Parry's comments highlight a classic procurement failure... politically driven cost-capping and capability-focus on one headline feature (AAW) at the expense of reliability, stealth, and numbers.
The PIP has made the ships usable in hot climates, but it doesn't erase the original design compromises — exactly as noted.
The Type 45s remain highly capable on paper for air defence, but they carry a legacy of shortcuts that continue to bite in real-world operations.
The RN plans to run them into the late 2030s/early 2040s alongside the incoming Type 83s, and there are very real concerns about capability gaps for air defence / destroyers as they continue to age...
TROUBLE PRONE UK PROCUREMENT SYSTEM:
The class will always be remembered as a cautionary tale in UK defence procurement... but a tail that keeps happening, in a procurement system that has long been exposed as prone to spirling costs, cuts to orders, spireling timelines of plans to production, to entering service, producing products that are often considered out of date by the time they enter service, and/or suffering so many cost or engineer driven compromises that they are insufficient for what they were designed for. UK Procurement issues go back decades and yet no one has done anything significant to change it.
Source ~ British & Commonwealth Forces F.B. Group.