HMS Defender comes out of dry dock as missile upgrade project progresses
HMS Defender came out of dry dock today as the complex programme to maintain and update the Type 45 destroyer moves ahead.
PIPKeep
HMS Defender began a complex £68M upkeep, engine replacement and weapons upgrade project in July 2023. She was taken into number 15 dry dock in Portsmouth, the hull was cut open and three new diesel generators inserted as the key work on the Power Improvement Project. Ultimately the PIP project aims to achieve 4 out of 6 Type 45s available (not necessarily at sea) by the end of 2025. (Although this is subject to the very challenging project to regenerate HMS Daring. The long period of dormancy, about 9 years without going to sea operationally, makes it much more difficult to bring the ship back into working condition).
Concurrently with PIP, Defender is also undergoing a major upkeep period, the ship has previously been run hard since her last major refit lasting 18 months completed in 2018.
Initial work has begun to modify the missile silo on the focsle.
CIP
HMS Defender is also in a Capability Insertion Period as the first of the Type 45s to be fitted with Sea Ceptor missiles housed in a separate 24-cell silo that will be added in front of the existing Sylver VLS silo. The additional silo is being manufactured separately ashore and will be lifted on to be embodied in the ship. She will also be fitted with the Naval Strike Missile, replacing the obsolete Harpoon anti-ship missile system as well as giving the Type 45s a modest land-attack capability for the first time. Defender is expected to return to the fleet in the Summer of 2026.
HMS Dragon is nearing the completion of her PIPKeep period and is due to begin sea trials soon. The unique Dragon artwork transfers have now been reapplied to both the port and starboard bows.
In October HMS Diamond began the same PIPKeep / weapon upgrade as HMS Defender but a higher level of Capability Insertion is required as she missed a refit a few years ago. She had an unplanned motor replacement that resulted in planned work being deferred. The Type 45s are also set to benefit from the Sea Viper Evolution programme which will equip them with anti-medium range ballistic missile capable Aster 30 Block 1 missiles, upgrades to the Sampson radar, Sea Viper command and control systems. IOC for SV-E is February 2028 with Diamond the first vessel to be equipped.
Source, which contains photos and other info at