Re: RN Aircraft Carriers: HMS Prince of Wales
Posted: Fri May 05, 2023 4:00 pm
HMS Prince of Wales – Shaft failure investigation results
On 3 April 2023, the Ministry of Defence submitted a letter to the House of Commons Defence Committee, providing details of the non-statutory investigation into the propulsion issues that affected HMS Prince of Wales.
The Minister of State, James Cartlidge, confirmed the conclusion of the investigation, which began after the ship suffered a starboard shaft coupling failure upon sailing from Portsmouth in August 2022.
The letter outlined that the investigation covered various aspects of the ship’s design, build, acceptance phases, and operations during Fleet time. The inquiry identified one causal factor as the misalignment of the starboard shaft from the build stage and the incorrect installation of key components. Several contributory factors led to this misalignment and the subsequent incorrect assessment of the starboard shaft and couplings’ performance.
“The causal factor identified in this instance was that PWLS starboard shaft was misaligned from build, and that the incorrect installation of key components resulted in the defect suffered.”
Sea Trials Reportedly Showed No Issues
According to the letter, during the ship’s sea trials, both shafts were extensively tested over several weeks and thousands of nautical miles. Vibration readings remained within limits at all times, and no issues, conditions of class, or actionable items were transferred into service from the Aircraft Carrier Alliance (ACA) to the Ministry of Defence (MOD) in 2019 at Vessel Acceptance.
“During PWLS’ sea trials, both shafts were extensively tested over several weeks and thousands of nautical miles in the Northern North Sea and UK South Coast Exercise Areas. Vibration readings remained within limits at all times. Accordingly, no issues, conditions of class or actionable items were transferred into service from the Aircraft Carrier Alliance (ACA) to the Ministry of Defence (MOD) in 2019 at Vessel Acceptance.”
Letter States Limited Operational Impact
The letter highlighted that following the August 2022 coupling failure, an alignment issue was also identified with the port shaft. Rectification work was initiated and is expected to be completed in time for the ship to commence her operational programme this autumn. It also mentioned that HMS Queen Elizabeth checked installation alignment readings, detecting no abnormalities. The operational impact of the defects on HMS Prince of Wales has been limited, with the Royal Navy delivering its Carrier commitments to NATO.
“The operational impact has been limited. HMS QNLZ undertook PWLS’s operational tasking from September to December 2022, after which she took over, as scheduled, as the Very High Readiness Strike Carrier. At all times the RN has delivered its Carrier commitments to NATO.”
Financial Cost and Future Actions Outlined in the Letter
The letter estimates the financial cost of the defect to be approximately £25 million. It notes that responsibility for payment has not yet been established and further comment on the matter would be inappropriate at this stage. The Department has reportedly conducted a preliminary examination of the investigation and the events that contributed to the defect, directing an urgent review.
“The financial cost is estimated to be approximately £25 million. Responsibility for payment has not yet been established therefore it would be inappropriate to comment further at this stage.”
Source UKDJ
On 3 April 2023, the Ministry of Defence submitted a letter to the House of Commons Defence Committee, providing details of the non-statutory investigation into the propulsion issues that affected HMS Prince of Wales.
The Minister of State, James Cartlidge, confirmed the conclusion of the investigation, which began after the ship suffered a starboard shaft coupling failure upon sailing from Portsmouth in August 2022.
The letter outlined that the investigation covered various aspects of the ship’s design, build, acceptance phases, and operations during Fleet time. The inquiry identified one causal factor as the misalignment of the starboard shaft from the build stage and the incorrect installation of key components. Several contributory factors led to this misalignment and the subsequent incorrect assessment of the starboard shaft and couplings’ performance.
“The causal factor identified in this instance was that PWLS starboard shaft was misaligned from build, and that the incorrect installation of key components resulted in the defect suffered.”
Sea Trials Reportedly Showed No Issues
According to the letter, during the ship’s sea trials, both shafts were extensively tested over several weeks and thousands of nautical miles. Vibration readings remained within limits at all times, and no issues, conditions of class, or actionable items were transferred into service from the Aircraft Carrier Alliance (ACA) to the Ministry of Defence (MOD) in 2019 at Vessel Acceptance.
“During PWLS’ sea trials, both shafts were extensively tested over several weeks and thousands of nautical miles in the Northern North Sea and UK South Coast Exercise Areas. Vibration readings remained within limits at all times. Accordingly, no issues, conditions of class or actionable items were transferred into service from the Aircraft Carrier Alliance (ACA) to the Ministry of Defence (MOD) in 2019 at Vessel Acceptance.”
Letter States Limited Operational Impact
The letter highlighted that following the August 2022 coupling failure, an alignment issue was also identified with the port shaft. Rectification work was initiated and is expected to be completed in time for the ship to commence her operational programme this autumn. It also mentioned that HMS Queen Elizabeth checked installation alignment readings, detecting no abnormalities. The operational impact of the defects on HMS Prince of Wales has been limited, with the Royal Navy delivering its Carrier commitments to NATO.
“The operational impact has been limited. HMS QNLZ undertook PWLS’s operational tasking from September to December 2022, after which she took over, as scheduled, as the Very High Readiness Strike Carrier. At all times the RN has delivered its Carrier commitments to NATO.”
Financial Cost and Future Actions Outlined in the Letter
The letter estimates the financial cost of the defect to be approximately £25 million. It notes that responsibility for payment has not yet been established and further comment on the matter would be inappropriate at this stage. The Department has reportedly conducted a preliminary examination of the investigation and the events that contributed to the defect, directing an urgent review.
“The financial cost is estimated to be approximately £25 million. Responsibility for payment has not yet been established therefore it would be inappropriate to comment further at this stage.”
Source UKDJ