Navy plans dry dock, waterfront production facility for subs at Pearl Harbor
[Refers to attached photo: The Navy has proposed rebuilding a submarine dry dock at Pearl Harbor Naval Shipyard, shown in the uppermost peninsula in this undated photograph of Pearl Harbor, Hawaii.]
HONOLULU (Tribune News Service) — For Pearl Harbor shipyard's first new dry dock since World War II, the Navy is reaching back in time and eyeing a pair of basins used during the war for ship work as the site for a huge new submarine repair facility.
Not only is the shipyard expected to get a massive waterfront production facility, it also may be able to perform work under wraps with a new adjacent covered dry dock being considered.
A Navy notice issued in May seeking industry feedback estimated the construction cost at between $2 billion and $4 billion.
Meeting ever-growing attack submarine needs in the Pacific to counter China requires four dry docks in Hawaii, the Navy said. Pearl has four, but Dry Dock 4 is used for surface ship work.
With the last work on older Los Angeles-class subs expected to end in 2022, the need becomes more acute.
Dry Dock 3, at only 497 feet, is headed for obsolescence because it can't accommodate even the current fleet of newer Virginia-class vessels, according to officials.
And Virginia subs are growing in size.
Los Angeles subs are 362 feet and displace 6, 900 tons. The 377-foot Virginia-class displaces 7, 800 tons.
The newest Virginia vessels being built with what's known as a "Virginia Payload Module " will have an additional 84-foot midbody section — meaning 460 feet in total length — with four vertical launch tubes capable of firing an additional 28 Tomahawk missiles.
The newest $3.4 billion Virginia subs, which are planned for delivery starting in 2025, displace 10, 200 tons. The new USS Arizona, SSN-803, will be the first with the Virginia Payload Module. Navy plans call for delivery of the new Arizona in late 2025.
A next-generation attack submarine expected in the 2030s will have a wider hull than the Virginia subs, meanwhile.
Dry Dock 3 is relatively shallow and can only support Los Angeles-class submarines with the use of "buoyancy assist modules " to lift the submarines sufficiently to enter the dry dock, said shipyard spokeswoman Kate Necaise.
The lift modules do not have capacity or straps suitable for the bigger Virginia submarines, and as a result, a deeper dry dock is being pursued to service those subs, she said.