Getting boats to sea – efforts to improve Royal Navy submarine availability
With the RN attack submarine fleet down to just 5 boats and the pressure of maintaining the nuclear deterrent unrelenting, initiatives to improve submarine reliability and availability have never been more important. Here we look at what is being done to mitigate chronic legacy issues and increase the time submarines spend at sea.
Background
The UK submarine procurement and support enterprise is an exceptionally complex, expensive and demanding endeavour with many interdependencies and difficulties that stem from poor decisions in the past. The two biggest single historical errors were made by politicians. When the Vanguard-class construction finished in the late 1990s a lack of orders to keep production going led to an exodus of submarine designers and builders, ultimately delaying the Astute class programme by almost a decade. The 2010 decision to delay the Dreadnought programme by five years means the Vanguard-class boat’s (originally designed for a 25-year service life) life-extension refits must keep them running for 40 years. Keeping 30-40 year old boats safe and operationally effective will be extremely demanding.
Much of the work of this colossal enterprise has to be done out of sight, in a highly restricted and regulated environment beyond much public scrutiny or understanding. From a national security perspective, a failure of the submarine force is not an option as the nuclear deterrent is UK defence priority one and is more relevant in 2022 than ever. If you were designing the RN from scratch right now, arguably a much larger proportion would be devoted to the underwater battlespace. Any adversary navy looking to take on the RN in the next few years at least, would undoubtedly consider the capabilities of the SSNs their single biggest concern.
There are many challenges and issues that have resulted in endless delays and decreasing availability of submarines. Given their importance, unlike most areas of defence, lack of funding is not the main constraint, although planning decades-long programmes into annual budget cycles is still an issue. For the Submarine Delivery Authority (SDA) there are conflicting priorities in the lifecycle of boats. The build phase is focused on cost and delivery date, once in service, the focus is on support and availability and at the end of their life, environmental responsibility is the key driver of decisions.
There is a total reliance on monopoly suppliers for very specialised equipment from the 3 key primes, Babcock, BAES and Rolls Royce and well into the second and third tiers of the supply chain. There is very little duplication of key infrastructure, for example, boats can only be built in Barrow and SSBNs can only be refuelled in a single dry dock. Development of the supporting dock infrastructure for (ever-larger) future submarines has to be done concurrently with ongoing critical projects. Any disruption at these single points of failure can have knock-on effects for the rest of the enterprise, potentially multiplying delays and costs.
Recruiting and retaining nuclear-qualified staff from a finite pool of talent in a small industry continues to be a struggle. There are generally enough trainees and experienced veterans close to retirement but a lack of people in mid-career. Demand for these people is likely to be further stretched by an energy crisis that makes civilian nuclear power generation increasingly attractive. Many of these issues are common to the wider defence enterprise but the nuclear submarine world is especially complex, a high hazard mix comprising around 70 major systems that use approximately 100,000 critical components
Continues at -
https://www.navylookout.com/getting-boa ... ilability/