Re: Proposed Fleet Solid Support Ships
Posted: Wed Nov 06, 2019 3:15 pm
MoD halts £1bn international tender for support ships
The Ministry of Defence has suspended the controversial £1bn international tender for three Royal Navy support ships, raising hopes that the major naval contract will be reserved for UK shipyards.
The MoD on Tuesday informed bidders for the contract to build at least two 40,000-tonne Fleet Solid Support ships that the process was being halted in order to ensure that requirements could be met.
“It is clear that the current approach will not deliver the requirement,” the MoD told the Financial Times. “We are now considering the most appropriate way forward for the procurement project.”
With a general election set for December 12, industry insiders said they did not expect the process to restart until early next year.
The decision to halt the bidding will be seen as a victory for the three-year campaign by unions, shipbuilders and politicians to keep the contract in the UK. Three UK shipyards have fallen into severe financial difficulties in the past year, including Harland and Wolff, builder of the Titanic.
Many regard the suspension as a first step to reclassifying the vessels to be exempt from EU laws aimed at preventing protectionism.
“That is pretty much industry’s expectation,” said one person close to the situation.
The decision to suspend the tender came after John Parker, the industrialist who in 2016 set out a plan for a national shipbuilding strategy, delivered a mixed verdict on progress so far in carrying out his recommendations.
Our yards cannot compete against the unfair subsidies awarded by other nations, while our competitors would not dream of letting the UK bid for their contracts
Ross Murdoch, GMB. In a review published on Tuesday, he criticised the government’s approach on allocation of naval work to UK yards.
Sir John said the UK had adopted a policy “contrary to [that] in most developed economies, where all defence-funded vessels are built in home yards and utilising their national supply chain . . . I do not, as an industrialist, believe it to be the right strategic approach.”
The Royal Navy has long lobbied for the contract to go to an international bidder, believing that the vessels can be made much more cheaply in foreign shipyards, several sources said.
As a result, and unlike many other EU countries, the UK has not classified the support vessels as warships, despite the fact that they have defensive weapons. Under existing EU procurement rules, the contract must then be put out to international competition. However, under the terms of the competition, the MoD had the right to stop the tender.
It could also have been controversial in the run-up to the election, with the Labour party already taking the position that the vessels should be built in the UK.
The ships are required by the Royal Fleet Auxiliary (RFA) to supply the Royal Navy’s two new Queen Elizabeth-class aircraft carriers, and accompanying ships, with food, ammunition and other supplies when they are deployed around the world.
A decision on the winning bid was expected next year. However, the bidding process has not gone smoothly. Since May, all international bidders, with the exception of Spain’s Navantia, have pulled out of the competition. A consortium dubbed Team UK, comprising Britain’s main shipbuilders, BAE Systems, Babcock International, Cammell Laird and Rolls-Royce, remained in the race.
The decision to halt the tender will now raise questions over whether the consortium will continue or the members will have to compete against each other.
Much will depend on the conditions imposed by the MoD — for example, whether some of the troubled shipyards such as Harland and Wolff would be expected to participate, one person said.
Unions called on the government to reclassify the ships to allow the contract to be awarded to UK companies without international competition.
“The steel that would be involved in producing the fleet will provide a much-needed shot in the arm for that sector but moreover provide a boost to UK manufacturing which has been buffeted by Brexit uncertainty, said Steve Turner, Unite’s assistant general secretary for manufacturing. “This tender should never have gone out to international bidders. No comparable developed economy would have done so.”
Ross Murdoch, GMB national officer, said: “Our yards cannot compete against the unfair subsidies awarded by other nations, while our competitors would not dream of letting the UK bid for their contracts. The government must now back skilled UK workers and our steel industry by keeping the Fleet Solid Support contract in the UK and reserving future awards for our own yards.”
From - https://www.ft.com/content/39c16806-001 ... 5uskcMu5MA
FROM SAVE THE NAVY TODAY 6TH NOVEMBER
Why has the Royal Navy’s Fleet Solid Support Ship competition been suspended?
In a surprise move, the MoD confirmed yesterday that it has suspended the international tender process for up to 3 Fleet Solid Support (FSS) ships to be built for the Royal Fleet Auxiliary. Here we consider the context and possible reasons for this decision.
Hardly noticed as Parliament went into recess ahead of the general election, on 4th November the Defence Secretary announced the publication of Sir John Parker’s review of the implementation of the National Shipbuilding Strategy (NSbS). Sir John makes a broadly positive assessment on progress since his NSbS was adopted as government policy in 2017 but was far from content that all his recommendations have been acted on. (Full report available here)
Continues at - https://www.savetheroyalnavy.org/why-ha ... suspended/
[I will not copy the long article from the S.T.N. site as it will be available for some time]
The Ministry of Defence has suspended the controversial £1bn international tender for three Royal Navy support ships, raising hopes that the major naval contract will be reserved for UK shipyards.
The MoD on Tuesday informed bidders for the contract to build at least two 40,000-tonne Fleet Solid Support ships that the process was being halted in order to ensure that requirements could be met.
“It is clear that the current approach will not deliver the requirement,” the MoD told the Financial Times. “We are now considering the most appropriate way forward for the procurement project.”
With a general election set for December 12, industry insiders said they did not expect the process to restart until early next year.
The decision to halt the bidding will be seen as a victory for the three-year campaign by unions, shipbuilders and politicians to keep the contract in the UK. Three UK shipyards have fallen into severe financial difficulties in the past year, including Harland and Wolff, builder of the Titanic.
Many regard the suspension as a first step to reclassifying the vessels to be exempt from EU laws aimed at preventing protectionism.
“That is pretty much industry’s expectation,” said one person close to the situation.
The decision to suspend the tender came after John Parker, the industrialist who in 2016 set out a plan for a national shipbuilding strategy, delivered a mixed verdict on progress so far in carrying out his recommendations.
Our yards cannot compete against the unfair subsidies awarded by other nations, while our competitors would not dream of letting the UK bid for their contracts
Ross Murdoch, GMB. In a review published on Tuesday, he criticised the government’s approach on allocation of naval work to UK yards.
Sir John said the UK had adopted a policy “contrary to [that] in most developed economies, where all defence-funded vessels are built in home yards and utilising their national supply chain . . . I do not, as an industrialist, believe it to be the right strategic approach.”
The Royal Navy has long lobbied for the contract to go to an international bidder, believing that the vessels can be made much more cheaply in foreign shipyards, several sources said.
As a result, and unlike many other EU countries, the UK has not classified the support vessels as warships, despite the fact that they have defensive weapons. Under existing EU procurement rules, the contract must then be put out to international competition. However, under the terms of the competition, the MoD had the right to stop the tender.
It could also have been controversial in the run-up to the election, with the Labour party already taking the position that the vessels should be built in the UK.
The ships are required by the Royal Fleet Auxiliary (RFA) to supply the Royal Navy’s two new Queen Elizabeth-class aircraft carriers, and accompanying ships, with food, ammunition and other supplies when they are deployed around the world.
A decision on the winning bid was expected next year. However, the bidding process has not gone smoothly. Since May, all international bidders, with the exception of Spain’s Navantia, have pulled out of the competition. A consortium dubbed Team UK, comprising Britain’s main shipbuilders, BAE Systems, Babcock International, Cammell Laird and Rolls-Royce, remained in the race.
The decision to halt the tender will now raise questions over whether the consortium will continue or the members will have to compete against each other.
Much will depend on the conditions imposed by the MoD — for example, whether some of the troubled shipyards such as Harland and Wolff would be expected to participate, one person said.
Unions called on the government to reclassify the ships to allow the contract to be awarded to UK companies without international competition.
“The steel that would be involved in producing the fleet will provide a much-needed shot in the arm for that sector but moreover provide a boost to UK manufacturing which has been buffeted by Brexit uncertainty, said Steve Turner, Unite’s assistant general secretary for manufacturing. “This tender should never have gone out to international bidders. No comparable developed economy would have done so.”
Ross Murdoch, GMB national officer, said: “Our yards cannot compete against the unfair subsidies awarded by other nations, while our competitors would not dream of letting the UK bid for their contracts. The government must now back skilled UK workers and our steel industry by keeping the Fleet Solid Support contract in the UK and reserving future awards for our own yards.”
From - https://www.ft.com/content/39c16806-001 ... 5uskcMu5MA
FROM SAVE THE NAVY TODAY 6TH NOVEMBER
Why has the Royal Navy’s Fleet Solid Support Ship competition been suspended?
In a surprise move, the MoD confirmed yesterday that it has suspended the international tender process for up to 3 Fleet Solid Support (FSS) ships to be built for the Royal Fleet Auxiliary. Here we consider the context and possible reasons for this decision.
Hardly noticed as Parliament went into recess ahead of the general election, on 4th November the Defence Secretary announced the publication of Sir John Parker’s review of the implementation of the National Shipbuilding Strategy (NSbS). Sir John makes a broadly positive assessment on progress since his NSbS was adopted as government policy in 2017 but was far from content that all his recommendations have been acted on. (Full report available here)
Continues at - https://www.savetheroyalnavy.org/why-ha ... suspended/
[I will not copy the long article from the S.T.N. site as it will be available for some time]