Constellation Frigate Delivery Delayed 3 Years, Says Navy
This story has been updated to include comments from Navy officials.
THE PENTAGON – The lead ship in a new class of guided-missile frigates for the U.S. Navy may be up to three years late, USNI News has learned.
Constellation (FFG-62), under construction at Fincantieri Marinette Marine in Wisconsin, may not deliver to the fleet until 2029, three years later than the original 2026 delivery goal, according to a service shipbuilding review.
The program’s delay came to light as part of the 45-day shipbuilding review that Secretary of the Navy Carlos Del Toro ordered earlier this year. In addition to the frigate delay, the Navy confirmed delays in delivering aircraft carrier Enterprise (CVN-80), the lead boat for the Columbia-class ballistic missile nuclear submarine, and the Virginia-class attack boats.
In a one-page summary of the review, the service cited lead ship problems like design maturation, supply chain issues, and difficulty finding skilled workers as factors in the program delays.
The future USS District of Columbia (SSBN-826) is facing a 12 to 16-month delay, according to the Navy’s summary. Last month, USNI News reported that the Navy was looking at a potential one year delay for District of Columbia due to ongoing supplier issues.
Enterprise is facing an 18 to 16-month delay, while the Block IV Virginia-class attack boats are looking at a three-year delay. The Block V Virginia-class submarines, which are larger and feature the new Virginia Payload Module, are currently two years behind schedule. Delays for the Navy’s new T-AGOS(X) ocean surveillance ship, which Austal USA won a contract to build last year, depend on when the program starts new construction.
As for America-class amphibious assault ships, the San Antonio-class amphibious transport docks, the Arleigh Burke-class destroyers and the John Lewis-class fleet replenishment oilers, the deliveries are “late to contract” but “are stable and tracking to Program Manager estimates,” according to the Navy’s summary.
Continues https://news.usni.org/2024/04/02/conste ... -says-navy
Guided Missile Frigates: Constellation Class
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Navy Lookout
USN discovering (like the RAN) that massive rework of an existing warship design adds weight, cost and delays.
USS Constellation class now share only 15% commonality with original FREMM platform and lead vessel cost underestimated by 40%
https://news.usni.org/2024/05/29/conste ... e-says-gao
USN discovering (like the RAN) that massive rework of an existing warship design adds weight, cost and delays.
USS Constellation class now share only 15% commonality with original FREMM platform and lead vessel cost underestimated by 40%
https://news.usni.org/2024/05/29/conste ... e-says-gao
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Unstable design has stalled construction and compromised schedule for US Navy’s next-generation frigate
https://rina.org.uk/publications/warshi ... n-frigate/
https://rina.org.uk/publications/warshi ... n-frigate/
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Constellation-class: the US Navy’s struggle to forge a new generation of frigates
After the perceived failure of the Littoral Combat ship programme, the US Navy has shifted its focus back to building traditional frigates. In this piece, we examine the turbulent beginnings of the Constellation-class (FFG-62) project and look at the wider lessons for those involved in warship design and acquisition.
Background
In the early 21st Century, a faction in the US Navy believed that conflict with another peer state was becoming a remote possibility and the main concern was terrorism and a few rouge states. In this new world, ‘old-fashioned’ frigates were seen as obsolete and should be replaced by something more agile and exciting. With the highly successful Oliver Hazard Perry-class frigates in need of replacement, instead of developing a new frigate, the radical Littoral Combat Ship was chosen.
The LCS was intended to be light, fast and modular, able to adapt to different roles and optimised for asymmetric warfare in coastal waters. Without getting into the conceptual flaws, design issues and procurement mistakes, the programme has mostly proved to be a disaster. Having spent $billions, the USN is stuck with more than 30 ships with a mix of reliability issues, poor survivability and missing capabilities. While some have already been decommissioned, the USN is working hard to overcome their shortcomings and optimise them for their main utility in the surface strike role. Perhaps most significantly, the intended ASW mission package for the LCS has been cancelled.
The USN has continued to buy more of the excellent Arleigh Burke-class destroyers (a total of 117 likely to be built, now up on the Flight III variant). Based on a 1980s design, these ships have continually evolved but are now at the developmental limit of what can be done within the existing hull. Burkes form the backbone of the fleet and are exceptionally capable air defence assets but they are not the best ASW platforms.
Continues https://www.navylookout.com/constellati ... -frigates/
After the perceived failure of the Littoral Combat ship programme, the US Navy has shifted its focus back to building traditional frigates. In this piece, we examine the turbulent beginnings of the Constellation-class (FFG-62) project and look at the wider lessons for those involved in warship design and acquisition.
Background
In the early 21st Century, a faction in the US Navy believed that conflict with another peer state was becoming a remote possibility and the main concern was terrorism and a few rouge states. In this new world, ‘old-fashioned’ frigates were seen as obsolete and should be replaced by something more agile and exciting. With the highly successful Oliver Hazard Perry-class frigates in need of replacement, instead of developing a new frigate, the radical Littoral Combat Ship was chosen.
The LCS was intended to be light, fast and modular, able to adapt to different roles and optimised for asymmetric warfare in coastal waters. Without getting into the conceptual flaws, design issues and procurement mistakes, the programme has mostly proved to be a disaster. Having spent $billions, the USN is stuck with more than 30 ships with a mix of reliability issues, poor survivability and missing capabilities. While some have already been decommissioned, the USN is working hard to overcome their shortcomings and optimise them for their main utility in the surface strike role. Perhaps most significantly, the intended ASW mission package for the LCS has been cancelled.
The USN has continued to buy more of the excellent Arleigh Burke-class destroyers (a total of 117 likely to be built, now up on the Flight III variant). Based on a 1980s design, these ships have continually evolved but are now at the developmental limit of what can be done within the existing hull. Burkes form the backbone of the fleet and are exceptionally capable air defence assets but they are not the best ASW platforms.
Continues https://www.navylookout.com/constellati ... -frigates/
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Constellation-class: the US Navy’s struggle to forge a new generation of frigates
After the perceived failure of the Littoral Combat ship programme, the US Navy has shifted its focus back to building traditional frigates. In this piece, we examine the turbulent beginnings of the Constellation-class (FFG-62) project and look at the wider lessons for those involved in warship design and acquisition.
Background
In the early 21st Century, a faction in the US Navy believed that conflict with another peer state was becoming a remote possibility and the main concern was terrorism and a few rogue states. In this new world, ‘old-fashioned’ frigates were seen as obsolete and should be replaced by something more agile and exciting. With the highly successful Oliver Hazard Perry-class frigates in need of replacement, instead of developing a new frigate, the radical Littoral Combat Ship was chosen.
Continues https://www.navylookout.com/constellati ... -frigates/
After the perceived failure of the Littoral Combat ship programme, the US Navy has shifted its focus back to building traditional frigates. In this piece, we examine the turbulent beginnings of the Constellation-class (FFG-62) project and look at the wider lessons for those involved in warship design and acquisition.
Background
In the early 21st Century, a faction in the US Navy believed that conflict with another peer state was becoming a remote possibility and the main concern was terrorism and a few rogue states. In this new world, ‘old-fashioned’ frigates were seen as obsolete and should be replaced by something more agile and exciting. With the highly successful Oliver Hazard Perry-class frigates in need of replacement, instead of developing a new frigate, the radical Littoral Combat Ship was chosen.
Continues https://www.navylookout.com/constellati ... -frigates/
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Navy: Constellation Frigate Design Will be Ready in May, Second Yard Could Come in FY 2027
ARLINGTON, Va. – The Constellation-class frigate’s design should be mature enough for the shipbuilder to enter continuous production by May, the Navy’s top acquisition executive said this week.
The assessment from the Navy comes after the service earlier this year disclosed delays in completing the design of the 6,700-ton guided-missile frigate. Shipbuilder Fincantieri Marinette Marine was set to deliver the first frigate – Constellation (FFG-62) – in 2026, but now the delivery could be three years later.
“In the meantime, we’ve awarded that company a handful of different ships, and we’re going to get them to the place where they could build them at speed, knowing that we’re significantly delayed in getting the first ship out,” Navy assistant secretary for research, development and acquisition Nickolas Guertin said Wednesday.
Navy leadership was surprised by the problems plaguing the Constellation-class when the service assessed the program as part of Navy Secretary Carlos Del Toro’s 45-day shipbuilding review, Guertin said.
Continues https://news.usni.org/2024/12/13/navy-c ... in-fy-2027
ARLINGTON, Va. – The Constellation-class frigate’s design should be mature enough for the shipbuilder to enter continuous production by May, the Navy’s top acquisition executive said this week.
The assessment from the Navy comes after the service earlier this year disclosed delays in completing the design of the 6,700-ton guided-missile frigate. Shipbuilder Fincantieri Marinette Marine was set to deliver the first frigate – Constellation (FFG-62) – in 2026, but now the delivery could be three years later.
“In the meantime, we’ve awarded that company a handful of different ships, and we’re going to get them to the place where they could build them at speed, knowing that we’re significantly delayed in getting the first ship out,” Navy assistant secretary for research, development and acquisition Nickolas Guertin said Wednesday.
Navy leadership was surprised by the problems plaguing the Constellation-class when the service assessed the program as part of Navy Secretary Carlos Del Toro’s 45-day shipbuilding review, Guertin said.
Continues https://news.usni.org/2024/12/13/navy-c ... in-fy-2027
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
US Navy seeks second yard for Constellation-class frigates
The US Navy is considering recruiting a second yard to help build its new class of guided missile frigates as the programme falls further and further behind schedule. In November, amid mounting concern over the delays and cost, the US Department of Defense issued a request for information (RfI) for a second yard to build the vessels, in addition to current builder Fincantieri Marinette Marine.
See https://rina.org.uk/publications/the-na ... -frigates/ LFT
The US Navy is considering recruiting a second yard to help build its new class of guided missile frigates as the programme falls further and further behind schedule. In November, amid mounting concern over the delays and cost, the US Department of Defense issued a request for information (RfI) for a second yard to build the vessels, in addition to current builder Fincantieri Marinette Marine.
See https://rina.org.uk/publications/the-na ... -frigates/ LFT
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Navy Lookout
US Navy has cancelled the Constellation-class frigate programme (First 2 ships will be completed).
Predictable delays and spiralling costs resulted from the decision to re-work 80% of the FREMM baseline design.
US Navy has cancelled the Constellation-class frigate programme (First 2 ships will be completed).
Predictable delays and spiralling costs resulted from the decision to re-work 80% of the FREMM baseline design.
You do not have the required permissions to view the files attached to this post.
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.
- Pelican
- Posts: 20059
- Joined: Thu Aug 09, 2018 10:10 pm
Re: Guided Missile Frigates: Constellation Class
Navy Lookout
BREAKING:
Following the cancellation of all but 2 of the Constellation class frigates, SECNAV has announced the USN will buy frigates based on the Legend-class National Coast Guard cutter.
Although a proven hull design the cutter does not meet warship survivability standards - will NAVSEA be able to resist similar huge modifications that messed up the Constellation programme?
BREAKING:
Following the cancellation of all but 2 of the Constellation class frigates, SECNAV has announced the USN will buy frigates based on the Legend-class National Coast Guard cutter.
Although a proven hull design the cutter does not meet warship survivability standards - will NAVSEA be able to resist similar huge modifications that messed up the Constellation programme?
You do not have the required permissions to view the files attached to this post.
HMS Pelican 1938 - 1958 GGCV L86 U86 F86 What I Have I Hold ~ A wonderful bird is the Pelican its beak can hold more than its belly can.